Lucas Berger cd7c177553 docs(10.1-01): complete foundation and domain analysis plan
Tasks completed: 3/3
- Rename sub-workflows to shorter pattern
- Analyze main workflow domain boundaries
- User approval on extraction boundaries

SUMMARY: .planning/phases/10.1-aggressive-workflow-modularization/10.1-01-SUMMARY.md
2026-02-04 21:10:07 -05:00

4.1 KiB

phase, plan, subsystem, tags, requires, provides, affects, tech-stack, key-files, key-decisions, patterns-established, duration, completed
phase plan subsystem tags requires provides affects tech-stack key-files key-decisions patterns-established duration completed
10.1-aggressive-workflow-modularization 01 workflow
n8n
modularization
refactoring
sub-workflows
domain-analysis
phase provides
10-workflow-modularization Initial sub-workflow extraction (Update, Actions, Logs)
Renamed sub-workflow files (n8n-update.json, n8n-actions.json, n8n-logs.json)
Domain boundary analysis for main workflow extraction
User-approved extraction plan for Waves 2-3
10.1-02
10.1-03
10.1-04
10.1-05
added patterns
Domain boundary analysis methodology for n8n workflows
Sub-workflow naming convention: n8n-{domain}.json
created modified
.planning/phases/10.1-aggressive-workflow-modularization/10.1-01-domain-analysis.md
n8n-update.json (renamed from n8n-container-update.json)
n8n-actions.json (renamed from n8n-container-actions.json)
n8n-logs.json (renamed from n8n-container-logs.json)
Shortened sub-workflow file naming to n8n-{domain}.json pattern
Realistic target: 115-125 nodes (not 50-80) due to 58 locked Telegram response nodes
Wave 2: Extract Batch UI and Container List domains
Wave 3: Extract Confirmation Dialogs and optionally Matching domain
Domain extraction prioritization: cohesion > size > complexity
Baseline node count calculation: locked nodes + infrastructure = minimum
~15min 2026-02-05

Phase 10.1 Plan 01: Foundation and Domain Analysis Summary

Renamed sub-workflows to n8n-{domain}.json pattern and established user-approved domain extraction boundaries targeting 115-125 nodes

Performance

  • Duration: ~15 min
  • Started: 2026-02-04
  • Completed: 2026-02-05T02:08:59Z
  • Tasks: 3
  • Files modified: 4 (3 renamed, 1 created)

Accomplishments

  • Renamed 3 sub-workflow files to shorter, consistent pattern (n8n-update.json, n8n-actions.json, n8n-logs.json)
  • Analyzed all 192 nodes in main workflow for domain extraction potential
  • Identified 4 extractable domains: Batch UI (48 nodes), Container List (17 nodes), Confirmation (30 nodes), Matching (15 nodes)
  • Established realistic target of 115-125 nodes (down from 192), accounting for 58 locked Telegram response nodes
  • Received user approval on extraction boundaries

Task Commits

Each task was committed atomically:

  1. Task 1: Rename sub-workflows - ff532aa (refactor)
  2. Task 2: Analyze domain boundaries - fba90a6 (docs)
  3. Task 3: User approval checkpoint - resolved via approval

Plan metadata: (this commit)

Files Created/Modified

  • n8n-update.json - Renamed from n8n-container-update.json
  • n8n-actions.json - Renamed from n8n-container-actions.json
  • n8n-logs.json - Renamed from n8n-container-logs.json
  • .planning/phases/10.1-aggressive-workflow-modularization/10.1-01-domain-analysis.md - Complete domain analysis with extraction recommendations

Decisions Made

  1. Realistic node target adjustment: Changed target from 50-80 nodes to 115-125 nodes after discovering 58 Telegram response nodes are locked to main workflow per CONTEXT.md
  2. Wave prioritization: Batch UI and Container List for Wave 2 (highest value), Confirmation and Matching for Wave 3
  3. Domains NOT extracted: Telegram responses (locked decision), Update All (too small, merge with Batch), Action Routing (infrastructure)

Deviations from Plan

None - plan executed exactly as written.

Issues Encountered

None - analysis completed as expected, user approved boundaries without modifications.

User Setup Required

None - no external service configuration required.

Next Phase Readiness

Ready to proceed with Wave 2 execution:

  • Plan 10.1-02: Extract Batch UI/Orchestration sub-workflow (target: 30-35 node reduction)
  • Plan 10.1-03: Extract Container List/Menu sub-workflow (target: 12-15 node reduction)

No blockers. Domain boundaries are clearly defined with entry/exit points documented.


Phase: 10.1-aggressive-workflow-modularization Completed: 2026-02-05