Lucas Berger 6e74b3fc05 docs: capture D-14/D-15 (Gate 2 deferral + local-Newt test rig) + deployment runbook
- docs/deployment.md: operator runbook — Mode A (local Newt test rig) vs Mode B (Unraid
  prod), Authelia client block, env reference, Pangolin SSE idle-timeout note, Gate 2 checklist.
- ROADMAP: Phase 1 verification-status note (Gate 1 done, Gate 2 deferred); Phase 3 gains live
  AUTH + iOS standalone-PWA criterion; Phase 4 gains hard SSE-smoke entry gate (#1034).
- PROJECT.md: D-14 (Gate 2 deferral split) + D-15 (local Newt rig); CAL-08 marked validated.
- STATE: decisions/blockers updated to reflect deferral and dev-auth-bypass approach.
2026-06-04 11:55:31 -04:00

98 lines
4.0 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
---
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
status: executing
stopped_at: Phase 1 context gathered
last_updated: "2026-06-04T13:45:46.863Z"
last_activity: 2026-06-04 -- Phase 01 execution started
progress:
total_phases: 5
completed_phases: 0
total_plans: 4
completed_plans: 0
percent: 0
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-06-03)
**Core value:** One color-coded family calendar (shared + personal) and shared lists from a single low-friction PWA — cross-ecosystem, no app store
**Current focus:** Phase 01 — foundation-broker-spike
## Current Position
Phase: 01 (foundation-broker-spike) — EXECUTING
Plan: 1 of 4
Status: Executing Phase 01
Last activity: 2026-06-04 -- Phase 01 execution started
Progress: [░░░░░░░░░░] 0%
## Performance Metrics
**Velocity:**
- Total plans completed: 0
- Average duration: -
- Total execution time: 0 hours
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| - | - | - | - |
**Recent Trend:**
- Last 5 plans: -
- Trend: -
*Updated after each plan completion*
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table.
Recent decisions affecting current work:
- CAL-08 RESOLVED → GO (Phase 1): per-member Fastmail app password reaches all of that account's calendars; no cross-account ACL needed. Unified view stands; no shared-only fallback. See CAL-08-DECISION.md.
- D-14 (2026-06-04): Phase 1 Gate 2 (live Authelia/Pangolin) deferred. SSE-over-Pangolin smoke = hard gate before Phase 4; live AUTH smoke incl. iOS standalone-PWA folded into Phase 3. Phases 23 build behind a dev-auth bypass. Tracked in 01-HUMAN-UAT.md + docs/deployment.md.
- D-15 (2026-06-04): Validate real topology via local Newt connector + test subdomain through Pangolin (Mode A), not an Unraid deploy; Unraid reserved for go-live.
- CalDAV locked: Fastmail does not expose calendars over JMAP. CalDAV via tsdav is the only protocol. No reconsideration.
- Identity: Use oidc_iss + oidc_sub as stable composite key. Never email.
- Real-time transport: Prefer SSE over WebSocket (proxy-resilient through Pangolin). SSE pass-through STILL UNVERIFIED — gate before Phase 4 (D-14).
- Recurring events: Create + display only in v1 (CALDAV:expand on server side). Single-occurrence edit deferred to v1.x.
### Pending Todos
None yet.
### Blockers/Concerns
- ~~Phase 1: Personal-calendar CalDAV ACL~~ RESOLVED → CAL-08 GO (per-member app password; no cross-account ACL).
- Phase 4 ENTRY GATE: Pangolin SSE pass-through (issue #1034) still unverified — deferred from Phase 1 Gate 2 (D-14). Must pass the 5-min SSE smoke (docs/deployment.md) before building live sync.
- Phase 3: iOS standalone-PWA + Authelia login is load-bearing for the wife and is the first real external auth test (carried Gate 2 item, D-14). Also: iOS install guide is load-bearing — she gets no push notifications if she does not install the PWA.
- Phase 2/3 dev: build behind a documented dev-auth bypass until Gate 2 deploy (D-14).
- Phase 5: iOS push subscriptions silently revoked after 3 silent pushes. Subscription health-check and event.waitUntil() are mandatory from day one.
## Deferred Items
| Category | Item | Status | Deferred At |
|----------|------|--------|-------------|
| Calendar | Single-occurrence recurring edit (RECURRENCE-ID) | v1.x | Roadmap |
| Calendar | "This and following" recurring edit | v1.x | Roadmap |
| Calendar | Apple Calendar native subscribe URL docs | v1.x | Roadmap |
| Calendar | Secondary timezone display toggle | v1.x | Roadmap |
| Display | Wall-display / kiosk dashboard | v2 | PROJECT.md |
## Session Continuity
Last session: 2026-06-04
Stopped at: Phase 1 code + Gate 1 complete (CAL-01/CAL-08 proven live). Gate 2 (live Authelia/Pangolin + SSE) deferred per D-14, tracked in 01-HUMAN-UAT.md + docs/deployment.md. Decisions D-14/D-15 logged. Ready to plan Phase 2.
Resume file: .planning/phases/01-foundation-broker-spike/01-HUMAN-UAT.md