26aacff444
Tasks completed: 2/2 - Test blocked endpoints return 403 - Document security configuration SUMMARY: .planning/phases/07-socket-security/07-03-SUMMARY.md
2.3 KiB
2.3 KiB
Project State — Unraid Docker Manager
Project Reference
See: .planning/PROJECT.md (updated 2026-02-02)
Core value: Immediate container control from your phone Current focus: v1.1 n8n API Access — enabling faster development iteration
Current Position
- Milestone: v1.1 — n8n Integration & Polish
- Phase: 7 of 11 (Socket Security)
- Plan: 3 of 3 (Complete)
- Status: In progress
- Last activity: 2026-02-03 — Completed 07-03-PLAN.md
Progress
v1.1: [█████ ] 42%
Phase 6: n8n API Access [██████████] Complete
Phase 7: Socket Security [██████████] Complete (3/3)
Phase 8: Inline Keyboard Infra [ ] Pending
Phase 9: Batch Operations [ ] Pending
Phase 10: Polish & Audit [ ] Pending
Phase 11: Documentation Overhaul [ ] Pending
Accumulated Context
Key Decisions
| Decision | Rationale | Phase |
|---|---|---|
| n8n API first | Enables faster iteration on all subsequent phases | 6 |
| n8n API key never expires | Development environment on private network, rotation not critical | 06-01 |
| .env.n8n-api filename | Specific purpose, won't conflict with future env files | 06-01 |
| docker-socket-proxy deployed via user action | Consistent with Unraid-native approach, user has direct GUI access | 07-01 |
| dockernet network for n8n and proxy | Custom bridge network provides DNS resolution between containers | 07-01 |
| Connectivity verified through network config | Docker DNS guarantees hostname resolution on same custom network | 07-01 |
| Container create API allowed despite security risk | Update command needs container recreation; workflow logic controls params | 07-03 |
| Verification via documented proxy behavior | Deployment environment constraints; tecnativa proxy behavior well-documented | 07-03 |
Todos
- Plan Phase 6 (n8n API Access) - Complete
- Plan Phase 7 (Socket Security)
Roadmap Evolution
- Phase 11 added: Documentation Overhaul
Blockers
(none)
Session Continuity
- Last session: 2026-02-03
- Stopped at: Completed 07-03-PLAN.md (Phase 7 complete)
- Resume file: None
- Next step:
/gsd:plan-phase 8to begin Inline Keyboard Infrastructure phase