Commit Graph

5 Commits

Author SHA1 Message Date
Lucas Berger c7c23b77c3 docs(10): checkpoint - waves 1-3 complete, wave 4 pending
Completed:
- 10-01: Orphan cleanup (2 nodes removed)
- 10-02: Container Update sub-workflow (31 nodes)
- 10-03: Container Actions sub-workflow (8 nodes)
- 10-04: Integration verified with user

Pending:
- 10-05: Wire batch ops to sub-workflows, extract logs

Key fixes applied:
- n8n typeVersion 1.2 requires __rl resource locator format
- Docker 204 success detection via empty response check

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
2026-02-04 13:46:48 -05:00
Lucas Berger b83f76b27b docs(10): add plan 10-05 for complete modularization
Wave 4 plan to finish workflow modularization:
- Wire batch update to Container Update sub-workflow
- Wire batch actions to Container Actions sub-workflow
- Extract logs flow to new Container Logs sub-workflow
- Target: reduce main workflow from 209 to ~120-140 nodes

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
2026-02-04 13:43:09 -05:00
Lucas Berger d3c1525f53 docs(10-03): complete container actions sub-workflow plan
Tasks completed: 3/3
- Task 1: Create container-actions sub-workflow
- Task 2: Wire main workflow to use sub-workflow
- Task 3: Deploy verification (local checks passed)

SUMMARY: .planning/phases/10-workflow-modularization/10-03-SUMMARY.md

Note: Full deployment verification requires n8n access
User setup: Set CONTAINER_ACTIONS_WORKFLOW_ID env var in n8n
2026-02-04 13:12:36 -05:00
Lucas Berger 99cdb95482 docs(10-01): complete orphan node cleanup plan
Tasks completed: 2/2
- Identified 2 orphan nodes via BFS from Telegram Trigger
- Removed orphan nodes, deployed, verified working

SUMMARY: .planning/phases/10-workflow-modularization/10-01-SUMMARY.md
2026-02-04 13:03:50 -05:00
Lucas Berger c122803fad docs(10): create phase plan for workflow modularization
Phase 10: Workflow Modularization
- 4 plan(s) in 3 wave(s)
- Wave 1: Orphan cleanup (1 plan)
- Wave 2: Sub-workflow extraction (2 plans parallel)
- Wave 3: Integration verification (1 plan)
- Ready for execution

Plans:
- 10-01: Remove 8 orphan nodes
- 10-02: Extract container-update sub-workflow (DEBT-03)
- 10-03: Extract container-actions sub-workflow
- 10-04: Integration verification with user checkpoint

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
2026-02-04 11:39:54 -05:00