Lucas Berger 245e4875c2 docs(phase-16): complete phase execution — all 6 plans finished
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 11:42:40 -05:00
Lucas Berger d5bc0be2fe docs(16-06): add critical lessons from hotfix to gap closure plan
Incorporates 5 lessons from commit 216f3a4 into the plan:
- Connection keys/targets must use node names, not IDs
- HTTP auth must use Header Auth credential, not manual env vars
- Node names must be unique
- Use $('Node Name') after GraphQL chains, not $input.item.json
- Added validation checklist to verification section

Marks Task 2 as already completed (dead code removal done in hotfix).
Updates node counts from 193 to 181 baseline.

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 11:31:53 -05:00
Lucas Berger c002ba8fd9 docs(16): add Phase 16 verification report with gap analysis
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 11:06:28 -05:00
Lucas Berger afda21cf3e docs(16-api-migration): create gap closure plan 16-06 2026-02-09 11:01:59 -05:00
Lucas Berger 93c74f9956 docs(16-05): complete main workflow GraphQL migration plan
Phase 16-05 SUMMARY:
- Task 1: Migrated 6 Docker API queries to Unraid GraphQL (GET → POST, added 12 nodes)
- Task 2: Analyzed callback data encoding (names used, token encoding unnecessary)
- Task 3: Implemented hybrid batch update (parallel for <=5, serial for >5 containers)

Updated STATE.md:
- Phase 16 marked complete (5/5 plans)
- Progress: 70% complete (7/10 plans in v1.4)
- Updated metrics: 57 plans total, 26 minutes for v1.4
- Added 3 key decisions from Phase 16-05
- Updated session info and next steps (Phase 17 ready)

Phase 16 API Migration complete. All workflows migrated to Unraid GraphQL API.
2026-02-09 10:39:31 -05:00
Lucas Berger 0610f05dc8 docs(16-02): complete Container Actions GraphQL Migration plan
- Container lifecycle operations (start/stop/restart) migrated to Unraid GraphQL
- Restart implemented as sequential stop+start chain
- ALREADY_IN_STATE errors map to HTTP 304
- Format Result nodes unchanged (zero-change migration)
- Duration: 3 minutes (2 tasks, 1 file, 2 commits)
2026-02-09 10:26:16 -05:00
Lucas Berger 50326b9ed7 docs(16-03): complete Container Update GraphQL migration
- SUMMARY.md documents single updateContainer mutation replacing 5-step Docker flow
- Workflow reduced from 34 to 29 nodes (15% reduction)
- 60-second timeout accommodates large image pulls
- ImageId comparison determines update success
- Zero Docker socket proxy references remaining
- STATE.md updated: Phase 16 now 3/5 plans complete (60%)
2026-02-09 10:25:59 -05:00
Lucas Berger bb3200f246 docs(16-01): complete Container Status migration plan
- SUMMARY: Container status queries migrated to Unraid GraphQL API
- STATE: Phase 16 progress updated (2/5 plans complete)
- Metrics: 2 minutes, 1 task, 1 file modified (n8n-status.json)
- Decisions: Inline Code nodes for normalizers, same query for all paths, registry update on every query
- Next: Plans 16-02, 16-03, 16-05 remaining
2026-02-09 10:24:59 -05:00
Lucas Berger 8e8a5f9dc3 docs(16-04): complete Batch UI GraphQL migration plan
- Created 16-04-SUMMARY.md with full execution details
- Updated STATE.md: Phase 16 in progress (1/5 plans)
- Recorded decisions: 5 normalizer nodes, 15s timeout
- Updated progress: v1.4 now 30% complete (3/10 plans)
2026-02-09 10:24:47 -05:00
Lucas Berger f84d433b25 fix(16): revise plans based on checker feedback 2026-02-09 09:25:17 -05:00
Lucas Berger 4fc791dd43 docs(16): create API migration phase plans (5 plans in 2 waves) 2026-02-09 09:19:10 -05:00
Lucas Berger 5880dc4573 docs(16): research Unraid GraphQL API migration patterns 2026-02-09 09:10:14 -05:00
Lucas Berger 6d5b407a8e docs(phase-15): complete phase execution 2026-02-09 09:00:37 -05:00
Lucas Berger 4e29bdeb56 docs(15-01): complete Container ID Registry and Callback Token Encoding plan
- Added 15-01-SUMMARY.md documenting implementation and deviations
- Updated STATE.md: Phase 15 complete (2/2 plans), 52 total plans, v1.4 at 20%
- Task 1 (Container ID Registry) was pre-existing in baseline
- Task 2 (Token Encoder/Decoder) implemented and pushed to n8n
- All utility nodes standalone, ready for Phase 16 wiring

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 08:56:03 -05:00
Lucas Berger d25fc1b13f docs(15-02): complete GraphQL utility nodes plan 2026-02-09 08:55:01 -05:00
Lucas Berger a352b15954 docs(15): create phase plan — 2 plans for infrastructure foundation 2026-02-09 08:42:39 -05:00
Lucas Berger 62eaa4b1ec docs(15): research infrastructure foundation domain 2026-02-09 08:36:44 -05:00
Lucas Berger 903e73d616 feat: v1.3 Unraid Update Status Sync
Unraid GraphQL API foundation — connectivity, authentication, and
container ID format verified for native Unraid API integration.

Phase 14: Unraid API Access (2 plans, 4 tasks)
- Established Unraid GraphQL API connectivity via myunraid.net cloud relay
- Dual credential storage (.env.unraid-api + n8n env vars)
- Container ID format: {server_hash}:{container_hash} (128-char SHA256 pair)
- Complete API contract documented in ARCHITECTURE.md
- "unraid" test command added to Telegram bot

Phases 15-16 dropped (superseded by v1.4 Unraid API Native).

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-09 07:47:31 -05:00
Lucas Berger ff0773b84b docs(14): create phase plan 2026-02-08 20:22:11 -05:00
Lucas Berger 00f0dcfd21 docs(14): research Unraid GraphQL API access patterns 2026-02-08 20:16:06 -05:00
Lucas Berger 9385deb0da docs(14): capture phase context 2026-02-08 20:10:58 -05:00
Lucas Berger 4b82044031 docs(phase-13): complete phase execution 2026-02-08 18:56:44 -05:00
Lucas Berger 4228cca9a3 docs(13-01): complete documentation overhaul plan
- README expanded from 139 to 264 lines (+90%)
- Added Architecture, Configuration, and Troubleshooting sections
- Documented all v1.2 features (batch selection, Update All button, inline keyboard)
- Removed outdated DEPLOYMENT_GUIDE.md (Phase 10-05, 3 sub-workflows)
- Consolidated to single technical reference: DEPLOY-SUBWORKFLOWS.md
- Updated STATE.md: Phase 13 complete, v1.2 milestone 100% COMPLETE
- Created 13-01-SUMMARY.md with full execution record

Phase 13-01 duration: 113 seconds
Tasks: 2/2 complete
Commits: 54437aa, a483bfb
2026-02-08 18:56:44 -05:00
Lucas Berger 70115f7cd6 docs(13): create phase plan 2026-02-08 18:56:44 -05:00
Lucas Berger 820dff47f4 docs(13): research documentation overhaul requirements and best practices 2026-02-08 18:56:44 -05:00
Lucas Berger afddb6130a docs(12-02): complete Phase 12 — all v1.2 requirements closed
BATCH-04 and BATCH-05 UAT passed. 9 bugs fixed during testing.
All 12 v1.2 requirements now complete. Phase 13 (docs overhaul) next.

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-08 18:56:44 -05:00
Lucas Berger b3909f00e5 docs(12-01): complete documentation audit plan
- Create 12-01-SUMMARY.md with execution metrics and decisions
- Update STATE.md: Phase 12 complete (1/1 plan)
- Record decision: Document Unraid limitation vs programmatic fix
- Closed 4 requirements: ENV-01, ENV-02, DEBT-01, DEBT-02
- Resolved UNR-01 as documented limitation
- Duration: 140 seconds, 2 tasks completed, 3 files modified

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-08 18:56:44 -05:00
Lucas Berger 1ef726942a docs(12): plan phase with Unraid badge research and UAT
Research found Unraid badge issue is architectural (bot bypasses
Unraid's XML template system). Updated plans to document limitation
with workaround instead of attempting programmatic fix. Plan 01
covers docs/env/debt, Plan 02 covers deferred Update All UAT.

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-08 18:56:44 -05:00
Lucas Berger 510b7d50dc docs(12): create phase plan 2026-02-08 18:56:44 -05:00
Lucas Berger c1d988f0e7 docs(12): research phase domain 2026-02-08 18:56:44 -05:00
Lucas Berger 732f692544 docs(12): capture phase context 2026-02-08 18:56:44 -05:00
Lucas Berger a15df26b7b docs(phase-11): complete phase execution — bitmap encoding + Update All
Verification: 7/9 must-haves pass, 2 deferred (Update All UAT → Phase 12).

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-08 18:56:44 -05:00
Lucas Berger 642d1ec73d docs(11-02): complete plan — Update All button, deployment, UAT
UAT results: tests 1-3,6 pass (bitmap, long names, batch exec, regression).
Tests 4-5 (Update All UAT) deferred to after Phase 12.

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-08 18:56:44 -05:00
Lucas Berger 339b366bcc docs(11-01): complete bitmap encoding plan -- unlimited container selection
- Created 11-01-SUMMARY.md with technical details and verification results
- Updated STATE.md: Phase 11 plan 1/2 complete, 50% progress
- Key metrics: 5m 16s duration, 2 tasks, 4 nodes added (1 batch-ui + 3 main workflow)
- Node counts: n8n-batch-ui.json 17 nodes, n8n-workflow.json 171 nodes
- Decisions: base36 BigInt encoding, graceful migration via dual parsers
2026-02-08 18:56:44 -05:00
Lucas Berger 1245aeed4f docs(11): create phase plan — bitmap batch selection + update all button 2026-02-08 18:56:44 -05:00
Lucas Berger 23ba84ae4e docs(11): research phase domain 2026-02-08 18:56:44 -05:00
Lucas Berger d2c44c0254 docs(phase-10.2): complete phase verification — all gaps closed 2026-02-08 18:56:44 -05:00
Lucas Berger f86ed83d00 docs(10.2-04): update UAT status - gaps 1-3 closed, gap 4 accepted
- Updated UAT status to gap-closure-complete
- Marked gaps 1-3 as closed by 10.2-04-PLAN.md
- Marked gap 4 as accepted (minor, no scope creep)
2026-02-08 18:56:44 -05:00
Lucas Berger 642162e0d3 docs(10.2-04): complete gap closure plan
- Created 10.2-04-SUMMARY.md with execution details
- Updated STATE.md: 4/4 plans complete, correlation IDs wired
- Documented UAT gaps 1-3 closed (gap 4 accepted as minor)
- Final state: 168 nodes, correlation IDs functional
2026-02-08 18:56:44 -05:00
Lucas Berger 5434ef20d1 docs(10.2): create gap closure plan for correlation ID wiring 2026-02-08 18:56:44 -05:00
Lucas Berger c288fa1d39 test(10.2): complete UAT - 2 passed, 4 issues 2026-02-08 18:56:44 -05:00
Lucas Berger 03af26598f docs(phase-10.2): complete phase execution 2026-02-08 18:56:44 -05:00
Lucas Berger f620229cec docs(10.2-03): complete plan — scope reduction due to n8n static data limitation
- Created 10.2-03-SUMMARY.md documenting scope reduction and platform limitation
- Updated STATE.md: Phase 10.2 complete (3/3 plans)
- Documented critical finding: n8n static data does not persist between executions
- Final state: 170 nodes (168 baseline + 2 correlation ID generators)
- Correlation ID infrastructure and structured error returns retained
2026-02-08 18:56:44 -05:00
Lucas Berger 2ac0ba78bd docs(10.2-02): complete plan -- error propagation and correlation IDs
Summary:
- All 7 sub-workflows now return structured error objects
- Main workflow generates correlation IDs for request tracing
- Error detection active for 2 high-value paths
- 8 workflow JSON files modified (1 main + 7 sub-workflows)
- Main workflow: 172 -> 176 nodes (+4)
- Duration: 5.5 minutes
- Deviations: 2 (error detection scope reduced, logs trigger workaround)

STATE.md updates:
- Plan 2 of 3 complete (67% progress)
- Added achievements for 10.2-02
- Added 3 new decisions
- Updated next step to Plan 03
2026-02-08 18:56:44 -05:00
Lucas Berger 6833641ad1 docs(10.2-01): complete error ring buffer foundation plan
- Create 10.2-01-SUMMARY.md with full plan execution details
- Update STATE.md: Phase 10.2 plan 1 of 3 complete (33% progress)
- Document all technical decisions and architecture patterns
- Self-check verification passed: all files and commits present
- Duration: 156 seconds (2.6 minutes)
- Node count: 168 -> 172 (+4 nodes: 2 command, 2 utility)
- Ring buffer infrastructure ready for Plan 02 wiring
2026-02-08 18:56:44 -05:00
Lucas Berger c79a3fbf87 docs(10.2): plan phase — error ring buffer, sub-workflow error propagation, debug tracing
3 plans in 3 waves:
- Wave 1: Ring buffer foundation + hidden debug commands (/errors, /debug, /trace, /clear-errors)
- Wave 2: Structured error returns in all 7 sub-workflows + correlation ID tracking
- Wave 3: Debug mode tracing at sub-workflow boundaries + deployment verification

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-02-08 18:56:44 -05:00
Lucas Berger e9a84794b9 docs(10.2): create phase plan 2026-02-08 18:56:44 -05:00
Lucas Berger 0ef36ab4c8 docs(10.2): research phase domain 2026-02-08 18:56:44 -05:00
Lucas Berger df637c9286 docs(10.2): capture phase context 2026-02-08 18:56:44 -05:00
Lucas Berger 8db937683e docs(phase-10.1): complete phase execution 2026-02-08 18:56:44 -05:00