docs(10): checkpoint - waves 1-3 complete, wave 4 pending

Completed:
- 10-01: Orphan cleanup (2 nodes removed)
- 10-02: Container Update sub-workflow (31 nodes)
- 10-03: Container Actions sub-workflow (8 nodes)
- 10-04: Integration verified with user

Pending:
- 10-05: Wire batch ops to sub-workflows, extract logs

Key fixes applied:
- n8n typeVersion 1.2 requires __rl resource locator format
- Docker 204 success detection via empty response check

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
This commit is contained in:
Lucas Berger
2026-02-04 13:46:48 -05:00
parent b83f76b27b
commit c7c23b77c3
3 changed files with 107 additions and 55 deletions
@@ -0,0 +1,19 @@
---
phase: 10-workflow-modularization
plan: 04
completed: 2026-02-04
---
# Phase 10 Plan 4: Integration Verification Summary
**User verified modularized workflow works correctly**
## Status
- ✓ Stop action works via inline keyboard
- ✓ Success message displays correctly
- ✓ Sub-workflows callable from main workflow
## Remaining: Plan 10-05
- Wire batch operations to sub-workflows
- Extract logs to sub-workflow
- Target: reduce main workflow from 209 to ~120-140 nodes