docs(phase-11): complete phase execution — bitmap encoding + Update All

Verification: 7/9 must-haves pass, 2 deferred (Update All UAT → Phase 12).

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
This commit is contained in:
Lucas Berger
2026-02-08 16:44:10 -05:00
parent 642d1ec73d
commit a15df26b7b
2 changed files with 223 additions and 8 deletions
+8 -8
View File
@@ -113,14 +113,14 @@ Plans:
**Plans:** 2 plans
Plans:
- [ ] 11-01-PLAN.md — Bitmap-encoded batch selection (replaces CSV-in-callback to eliminate 64-byte limit)
- [ ] 11-02-PLAN.md — Update All inline keyboard button, deployment, and UAT verification
- [x] 11-01-PLAN.md — Bitmap-encoded batch selection (replaces CSV-in-callback to eliminate 64-byte limit)
- [x] 11-02-PLAN.md — Update All inline keyboard button, deployment, and UAT verification
**Success Criteria:**
1. User can type "update all" to update all :latest containers with confirmation
2. User can tap "Update All" in inline keyboard to update all :latest containers
3. Batch selection keyboard allows selecting 5+ containers without hitting callback limit
4. Containers with long names (20+ chars) can be selected in batch keyboard
1. User can type "update all" to update all :latest containers with confirmation (code deployed, UAT deferred to Phase 12)
2. User can tap "Update All" in inline keyboard to update all :latest containers (code deployed, UAT deferred to Phase 12)
3. Batch selection keyboard allows selecting 5+ containers without hitting callback limit
4. Containers with long names (20+ chars) can be selected in batch keyboard
---
@@ -177,11 +177,11 @@ Plans:
| 10 | Workflow Modularization | v1.2 | Complete |
| 10.1 | Aggressive Workflow Modularization | v1.2 | Complete |
| 10.2 | Better Logging & Log Management | v1.2 | Complete (descoped) |
| 11 | Update All & Callback Limits | v1.2 | Planning |
| 11 | Update All & Callback Limits | v1.2 | Complete (UAT partial, 2 deferred) |
| 12 | Polish & Audit | v1.2 | Pending |
| 13 | Documentation Overhaul | v1.2 | Pending |
**v1.2 Coverage:** 12+ requirements mapped across 7 phases
---
*Updated: 2026-02-08 — Phase 11 planned (2 plans in 2 waves)*
*Updated: 2026-02-08 — Phase 11 complete (bitmap encoding + Update All button deployed, 2 UAT tests deferred to Phase 12)*