docs(13-01): complete documentation overhaul plan
- README expanded from 139 to 264 lines (+90%) - Added Architecture, Configuration, and Troubleshooting sections - Documented all v1.2 features (batch selection, Update All button, inline keyboard) - Removed outdated DEPLOYMENT_GUIDE.md (Phase 10-05, 3 sub-workflows) - Consolidated to single technical reference: DEPLOY-SUBWORKFLOWS.md - Updated STATE.md: Phase 13 complete, v1.2 milestone 100% COMPLETE - Created 13-01-SUMMARY.md with full execution record Phase 13-01 duration: 113 seconds Tasks: 2/2 complete Commits: 54437aa, a483bfb
This commit is contained in:
+26
-8
@@ -3,10 +3,10 @@
|
||||
## Current Position
|
||||
|
||||
- **Milestone:** v1.2 -- Modularization & Polish
|
||||
- **Phase:** 12 of 13 (Polish & Audit)
|
||||
- **Plan:** 2 of 2 complete
|
||||
- **Status:** Phase 12 COMPLETE (documentation + UAT, all v1.2 requirements closed)
|
||||
- **Last activity:** 2026-02-08 -- Completed 12-02 (UAT: BATCH-04, BATCH-05 passed after 9 bug fixes)
|
||||
- **Phase:** 13 of 13 (Documentation Overhaul)
|
||||
- **Plan:** 1 of 1 complete
|
||||
- **Status:** Phase 13 COMPLETE (README overhaul, documentation consolidation)
|
||||
- **Last activity:** 2026-02-08 -- Completed 13-01 (README architecture/config/troubleshooting, removed outdated DEPLOYMENT_GUIDE.md)
|
||||
|
||||
## Progress
|
||||
|
||||
@@ -14,14 +14,14 @@
|
||||
v1.0: [**********] 100% SHIPPED
|
||||
v1.1: [**********] 100% SHIPPED
|
||||
|
||||
v1.2: [*********_] 83%
|
||||
v1.2: [**********] 100% COMPLETE
|
||||
|
||||
Phase 10: Workflow Modularization [**********] 100% COMPLETE (+ 10-07 UAT fixes)
|
||||
Phase 10.1: Aggressive Modularization [**********] 100% COMPLETE (9/9 plans + UAT closure)
|
||||
Phase 10.2: Better Logging & Log Management [**********] 100% COMPLETE (4/4 plans complete)
|
||||
Phase 11: Update All & Callback Limits [**********] 100% COMPLETE (2/2 plans, UAT 6/6 pass)
|
||||
Phase 12: Polish & Audit [**********] 100% COMPLETE (2/2 plans, all requirements closed)
|
||||
Phase 13: Documentation Overhaul [ ] Pending
|
||||
Phase 13: Documentation Overhaul [**********] 100% COMPLETE (1/1 plan, README overhaul)
|
||||
```
|
||||
|
||||
## Phase 10 Completion Summary
|
||||
@@ -134,6 +134,8 @@ Phase 13: Documentation Overhaul [ ] Pending
|
||||
- [Quick 1-1]: Removed 6 orphan callback nodes (no incoming connections after Phase 10 modularization)
|
||||
- [Quick 1-1]: Achieved structural minimum of 166 nodes (per Phase 10.1-07 analysis)
|
||||
- [Phase 12-01]: Document Unraid badge limitation instead of programmatic fix (Unraid API integration adds complexity for cosmetic issue)
|
||||
- [Phase 13-01]: Remove DEPLOYMENT_GUIDE.md instead of updating (outdated Phase 10-05 content, fully superseded by DEPLOY-SUBWORKFLOWS.md)
|
||||
- [Phase 13-01]: Separate Configuration from Installation in README (installation should be linear and action-only)
|
||||
|
||||
## Phase 10.1 Progress
|
||||
|
||||
@@ -252,6 +254,22 @@ All 7 sub-workflows deployed and operational:
|
||||
- Closed 4 requirements: ENV-01, ENV-02, DEBT-01, DEBT-02
|
||||
- Resolved UNR-01 as documented limitation (not a fix, but closed)
|
||||
|
||||
## Phase 13 Progress
|
||||
|
||||
| Plan | Description | Status |
|
||||
|------|-------------|--------|
|
||||
| 13-01 | README overhaul with architecture, configuration, troubleshooting | Complete |
|
||||
|
||||
**Achievements (13-01):**
|
||||
- README expanded from 139 to 264 lines with dedicated Architecture, Configuration, and Troubleshooting sections
|
||||
- Documented batch selection workflow (toggle checkmarks, multi-select UI in inline keyboard)
|
||||
- Documented "Update All :latest" button location and usage in inline keyboard
|
||||
- Separated configuration from installation (installation now linear and action-only)
|
||||
- Added 5 common troubleshooting scenarios with fixes
|
||||
- Removed outdated DEPLOYMENT_GUIDE.md (Phase 10-05, 3 sub-workflows, 199 nodes)
|
||||
- Consolidated to single technical reference: DEPLOY-SUBWORKFLOWS.md (725 lines, 7 sub-workflows, 166 nodes)
|
||||
- All v1.2 features now documented (batch ops, update all, inline keyboard, 7 sub-workflows)
|
||||
|
||||
## Quick Tasks Completed
|
||||
|
||||
| Task | Description | Status | Date | Node Impact |
|
||||
@@ -260,12 +278,12 @@ All 7 sub-workflows deployed and operational:
|
||||
|
||||
## Next Step
|
||||
|
||||
Phase 12 complete (documentation + UAT, all v1.2 requirements closed). Next: Phase 13 (Documentation Overhaul).
|
||||
Phase 13 complete (documentation overhaul). v1.2 milestone 100% COMPLETE. All requirements closed.
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-02-08
|
||||
Stopped at: Completed 12-02 (UAT: BATCH-04, BATCH-05 passed, 9 bug fixes, all v1.2 requirements closed)
|
||||
Stopped at: Completed 13-01 (README overhaul: architecture/config/troubleshooting, removed DEPLOYMENT_GUIDE.md)
|
||||
Resume file: None
|
||||
|
||||
---
|
||||
|
||||
Reference in New Issue
Block a user