--- context: phase phase: 02-calendar-display task: 0 total_tasks: 5 status: planned-not-executed last_updated: 2026-06-04T19:28:41.530Z --- Phase 2 (calendar-display) is **fully planned and verified, not yet executed**. The plan-checker PASSED on iteration 2 (the initial check found 2 blockers + 3 warnings; all were fixed). 5 PLAN.md files exist across 4 waves. Phase 1 already shipped a working pnpm monorepo (apps/api Hono+Drizzle+CalDAV broker, apps/pwa React+Vite). The immediate next step is execution: `/gsd-execute-phase 2`. One uncommitted file: `.planning/config.json` (this session's settings changes). This session: - Phase 2 RESEARCH.md + Nyquist VALIDATION.md written and committed (a707f8d) - PATTERNS.md written — 23 files classified, 19 analogs from Phase 1 code (5e14413) - 5 PLAN.md files created in 4 waves; plan-checker PASSED iteration 2 (fc4cc2c) - Requirements coverage 3/3 (CAL-02, CAL-03, CAL-07); decision coverage 10/10 - Backlog item 999.1 added — "treat Fastmail as a calendar provider, support more" (8bd52c6) - GSD config changed via /gsd-config: Adaptive profile, TDD on, per-milestone branching, auto-advance on; saved as global defaults (~/.gsd/defaults.json). **config.json uncommitted.** - Execute Phase 2 — run all 5 plans across 4 waves: - Wave 1: 02-01 — schema (has_rrule/is_shared) + **[BLOCKING] drizzle-kit push** + dev-auth bypass + PWA vitest/jsdom harness + ICS fixtures + RED stubs - Wave 2: 02-02 (backend: expandOccurrences + windowed /api/events) ∥ 02-03 (frontend foundation: tokens, colorUtils, calendarConfig, hydrateEvents, Zustand store) — no file overlap - Wave 3: 02-04 — CalendarShell renders REAL windowed Fastmail events, color-coded, 4 views - Wave 4: 02-05 — EventDetailPopover + ColorLegend + nav/toolbar + skeleton/empty/error + human verify - Server-side recurrence expansion via `ICAL.RecurExpansion`, with VTIMEZONE registered BEFORE expansion (or DST events render at wrong wall-clock time). - Schedule-X `calendarId = occ.isShared ? 'shared' : String(occ.ownerUserId)` — NOT `String(occ.calendarId)`. The calendars config is keyed by userId; using the DB calendar-row id silently breaks color routing for members owning multiple calendars. - Shared-family calendar identified via a `calendars.is_shared` column + operator checkpoint (chosen over fragile displayName matching). - This-session GSD config: Adaptive profile, TDD on, per-milestone branching, auto-advance on. - None. Clean pause between plan and execute. ## Required Reading (in order) 1. `.planning/phases/02-calendar-display/02-01-PLAN.md` … `02-05-PLAN.md` — the plans to execute 2. `.planning/phases/02-calendar-display/02-RESEARCH.md` — DST/VTIMEZONE, Schedule-X Temporal, firstDayOfWeek 0→7, has_rrule pre-filter (the landmines) 3. `.planning/phases/02-calendar-display/02-VALIDATION.md` — per-task verification map (Nyquist) 4. `.planning/phases/02-calendar-display/02-PATTERNS.md` — analog files in the Phase 1 codebase ## Critical Anti-Patterns (do NOT repeat these) - Do NOT skip the `[BLOCKING] npx drizzle-kit push` task in Wave 1 (02-01). Build/types pass without it because TS types come from config, not the live DB → false-positive verification. - Do NOT stamp `String(occ.calendarId)` as the Schedule-X calendarId — use isShared/ownerUserId. - Do NOT expand recurrences before registering VTIMEZONE; do NOT shift all-day events through UTC (keep them as 'YYYY-MM-DD' / Temporal.PlainDate). ## Infrastructure State - Branch: `main`. git.branching_strategy is now `milestone` — execute may create a milestone branch. - Phase 1 shipped: apps/api + apps/pwa, MariaDB via docker-compose. No background processes running. - TDD is ON globally now, but Phase 2 plans were written PRE-TDD — they carry no TDD gates. Only Phase 3+ will get TDD. (Re-plan Phase 2 if you want TDD gates here.) Everything went smoothly — no failures discovered, no rework beyond the one planned revision loop. The plans are execution-ready. The only thing a fresh agent must internalize is the auto-advance + per-milestone branching change made this session, and that TDD won't retroactively apply to Phase 2's already-written plans. Start with: `/gsd-execute-phase 2`. Two human checkpoints will pause execution — marking the shared-family calendar (Wave 2, plan 02-02) and final visual verification of the 4 success criteria (Wave 4, plan 02-05). Consider committing `.planning/config.json` first.