Lucas Berger
82ab87a633
docs(03-04): complete outbox worker plan — state machine GREEN, wired at boot
2026-06-05 18:23:01 -04:00
Lucas Berger
95864e5dc8
docs(03-07): complete PWA install plan — manifest, InstallPrompt, icons
2026-06-05 18:07:59 -04:00
Lucas Berger
7398946aa8
docs(03-03): complete write API surface plan — enqueue-only endpoints GREEN
2026-06-05 17:59:53 -04:00
Lucas Berger
4eb7c28797
docs(03-02): complete broker primitives plan — vevent.ts + write.ts GREEN
2026-06-05 17:50:23 -04:00
Lucas Berger
a487569c7e
docs(03-01): complete foundation-scaffold plan
2026-06-05 17:41:41 -04:00
Lucas Berger
9dd08d28d1
docs(03): create phase plan (8 plans, 5 waves)
2026-06-05 16:57:01 -04:00
Lucas Berger
edf9649a21
docs(phase-02): complete phase — mark roadmap + requirements traceability
2026-06-05 16:01:15 -04:00
Lucas Berger
00a4e66a8d
docs(phase-02): update tracking after wave 3
2026-06-05 10:44:57 -04:00
Lucas Berger
bfddcb1da2
docs(phase-02): update tracking after wave 2
2026-06-05 10:33:53 -04:00
Lucas Berger
6dc5d77f60
docs(phase-02): update tracking after wave 1
2026-06-05 09:38:23 -04:00
Lucas Berger
8bd52c6923
docs: add backlog item 999.1 — treat Fastmail as a calendar provider, support adding more
2026-06-04 15:12:20 -04:00
Lucas Berger
fc4cc2ccf8
docs(02): create phase plan
2026-06-04 15:09:55 -04:00
Lucas Berger
b842955612
docs(02): create calendar-display phase plan (5 plans, 4 waves)
2026-06-04 14:56:57 -04:00
Lucas Berger
6e74b3fc05
docs: capture D-14/D-15 (Gate 2 deferral + local-Newt test rig) + deployment runbook
...
- docs/deployment.md: operator runbook — Mode A (local Newt test rig) vs Mode B (Unraid
prod), Authelia client block, env reference, Pangolin SSE idle-timeout note, Gate 2 checklist.
- ROADMAP: Phase 1 verification-status note (Gate 1 done, Gate 2 deferred); Phase 3 gains live
AUTH + iOS standalone-PWA criterion; Phase 4 gains hard SSE-smoke entry gate (#1034 ).
- PROJECT.md: D-14 (Gate 2 deferral split) + D-15 (local Newt rig); CAL-08 marked validated.
- STATE: decisions/blockers updated to reflect deferral and dev-auth-bypass approach.
2026-06-04 11:55:31 -04:00
Lucas Berger
fe8d5c8e4b
docs(phase-01): mark 01-04 code complete after wave 3
2026-06-04 11:40:00 -04:00
Lucas Berger
d2d8333bf8
docs(phase-01): update tracking after wave 2 (01-02 OIDC, 01-03 broker)
2026-06-04 11:10:44 -04:00
Lucas Berger
ee4c71fa46
docs(01-01): clear Task 3 checkpoint, mark plan complete
...
Stack verified live (/health green, 4 tables pushed). Record Docker deviation in
SUMMARY, mark 01-01 complete in ROADMAP, clean up paused-setup handoff files.
2026-06-04 10:17:21 -04:00
Lucas Berger
3c51e423ff
docs(01-foundation-broker-spike): create phase plan (4 plans, 3 waves) + SKELETON + validation map
2026-06-04 08:16:48 -04:00
Lucas Berger
ac82d32a36
docs: create roadmap (5 phases)
2026-06-03 16:15:27 -04:00