wip: Phase 4 paused — discuss complete, entry gate cleared, ready to plan
This commit is contained in:
@@ -0,0 +1,35 @@
|
||||
{
|
||||
"version": "1.0",
|
||||
"timestamp": "2026-06-08T01:52:24.365Z",
|
||||
"phase": "4",
|
||||
"phase_name": "Shared Lists + Live Sync",
|
||||
"phase_dir": ".planning/phases/04-shared-lists-live-sync",
|
||||
"plan": null,
|
||||
"task": null,
|
||||
"total_tasks": null,
|
||||
"status": "paused",
|
||||
"stage": "discuss-complete; entry-gate-cleared; ready-to-plan",
|
||||
"completed_tasks": [
|
||||
{"id": 1, "name": "discuss-phase 4 → 04-CONTEXT.md + 04-DISCUSSION-LOG.md (18 decisions D-01..D-18)", "status": "done", "commit": "05e1c9e"},
|
||||
{"id": 2, "name": "Ran SSE-over-Pangolin smoke test live — PASS (~6 min, 35 heartbeats, buffering off, no cut)", "status": "done"},
|
||||
{"id": 3, "name": "Recorded gate PASS via quick task 260607-u8o (01-HUMAN-UAT item 4 + 03-GATE2-RESULTS Part C)", "status": "done", "commit": "9ee5906"},
|
||||
{"id": 4, "name": "Saved project memory: N-member expansion principle", "status": "done"}
|
||||
],
|
||||
"remaining_tasks": [
|
||||
{"id": 5, "name": "Plan Phase 4: /gsd-plan-phase 4 (reads 04-CONTEXT.md)", "status": "not_started"},
|
||||
{"id": 6, "name": "Optionally /gsd-ui-phase 4 for the lists UI design contract (UI hint: yes)", "status": "not_started"},
|
||||
{"id": 7, "name": "Execute Phase 4 plans", "status": "not_started"}
|
||||
],
|
||||
"blockers": [],
|
||||
"human_actions_pending": [
|
||||
{"action": "Log out / invalidate the Authelia session whose oidc-auth cookie was pasted into the transcript during the SSE test", "context": "Cookie embeds a refresh token valid until ~2026-06-08; it is now in conversation history. Non-blocking but a security hygiene follow-up.", "blocking": false}
|
||||
],
|
||||
"decisions": [
|
||||
{"decision": "Phase 4 entry gate (SSE-over-Pangolin, D-14/#1034) CLEARED", "rationale": "Live smoke test held a heartbeat stream open ~6 min through Pangolin with incremental delivery and no cut; buffering confirmed off", "phase": "4"},
|
||||
{"decision": "All Phase 4 implementation decisions captured in 04-CONTEXT.md (D-01..D-18)", "rationale": "Discuss-phase complete; downstream planner/researcher consume CONTEXT.md", "phase": "4"},
|
||||
{"decision": "Design member-count-agnostic (N family members, not hard-coded 2)", "rationale": "User stated future expansion; drives list_shares join table + per-list-scoped SSE fan-out", "phase": "4"}
|
||||
],
|
||||
"uncommitted_files": [],
|
||||
"next_action": "/clear then /gsd-plan-phase 4 (entry gate is cleared; no infra precondition remains)",
|
||||
"context_notes": "Phase 4 = app-native shared lists (MariaDB, NOT CalDAV) with SSE live co-edit sync. Discussion is done and committed; the SSE transport gate that was blocking the build is now verified and recorded. Nothing is mid-edit — clean stopping point between discuss and plan. Key locked choices for the planner: default-shared lists + private toggle via list_shares join table; checked items sink to completed section; optimistic UI + per-field PATCH last-write-wins (no CRDT); delete-wins; full-refetch-on-reconnect + capped-backoff + polling fallback; string fractional-index ordering; bottom tab bar + react-router. Open for planner: in-memory EventEmitter vs Redis pub/sub (single Node process today, ioredis not installed); new tables must use drizzle generate+migrate, NOT push."
|
||||
}
|
||||
Reference in New Issue
Block a user