@@ -65,8 +65,8 @@ Plans:
**Wave 2** *(blocked on Wave 1 completion)* **Wave 2** *(blocked on Wave 1 completion)*
- [ ] 02-02-PLAN.md — Backend slice: expandOccurrences() (VTIMEZONE/DST + all-day + EXDATE) + windowed/joined/zod-validated /api/events + shared-calendar checkpoint (CAL-02/CAL-07) - [x] 02-02-PLAN.md — Backend slice: expandOccurrences() (VTIMEZONE/DST + all-day + EXDATE) + windowed/joined/zod-validated /api/events + shared-calendar checkpoint (CAL-02/CAL-07)
- [ ] 02-03-PLAN.md — Frontend foundation: CSS token layer + colorUtils + calendarConfig (firstDayOfWeek 0→7) + hydrateEvents (Temporal/PlainDate guard) + Zustand store + windowed fetchEvents - [x] 02-03-PLAN.md — Frontend foundation: CSS token layer + colorUtils + calendarConfig (firstDayOfWeek 0→7) + hydrateEvents (Temporal/PlainDate guard) + Zustand store + windowed fetchEvents
**Wave 3** *(blocked on Wave 2 completion)* **Wave 3** *(blocked on Wave 2 completion)*
@@ -136,7 +136,7 @@ Note: Phase 4 depends only on Phase 1 and can begin as soon as Phase 1 is comple
| Phase | Plans Complete | Status | Completed | | Phase | Plans Complete | Status | Completed |
|-------|----------------|--------|-----------| |-------|----------------|--------|-----------|
| 1. Foundation + Broker Spike | 4/4 | Complete | 2026-06-04 | | 1. Foundation + Broker Spike | 4/4 | Complete | 2026-06-04 |
| 2. Calendar Display | 1/5 | In Progress| | | 2. Calendar Display | 3/5 | In Progress| |
| 3. Event Write-Back + PWA Install | 0/? | Not started | - | | 3. Event Write-Back + PWA Install | 0/? | Not started | - |
| 4. Shared Lists + Live Sync | 0/? | Not started | - | | 4. Shared Lists + Live Sync | 0/? | Not started | - |
| 5. Web Push Notifications | 0/? | Not started | - | | 5. Web Push Notifications | 0/? | Not started | - |
@@ -147,7 +147,7 @@ Note: Phase 4 depends only on Phase 1 and can begin as soon as Phase 1 is comple
**Goal:** [Captured for future planning] Abstract the calendar backend behind a provider interface so Fastmail/CalDAV is one implementation among potentially many. Shipping with a single provider is fine, but the broker, sync, and event-expansion layers should be structured so additional providers (e.g. other CalDAV hosts, Google Calendar, generic ICS feeds) can be added without rework. Captures the "provider" seam as an explicit architectural concern. **Goal:** [Captured for future planning] Abstract the calendar backend behind a provider interface so Fastmail/CalDAV is one implementation among potentially many. Shipping with a single provider is fine, but the broker, sync, and event-expansion layers should be structured so additional providers (e.g. other CalDAV hosts, Google Calendar, generic ICS feeds) can be added without rework. Captures the "provider" seam as an explicit architectural concern.
**Requirements:** TBD **Requirements:** TBD
**Plans:** 1/5 plans executed **Plans:** 3/5 plans executed
Plans: Plans: