docs(phase-20): update tracking after wave 1
This commit is contained in:
+10
-10
@@ -2,17 +2,17 @@
|
||||
gsd_state_version: 1.0
|
||||
milestone: v1.1
|
||||
milestone_name: Operability & Polish
|
||||
current_phase: 18
|
||||
current_phase_name: Auto timezone detection and ability to change timezone
|
||||
current_phase: 20
|
||||
current_phase_name: admin-member-editor-form-declutter
|
||||
status: executing
|
||||
stopped_at: Phase 20 UI-SPEC approved
|
||||
last_updated: "2026-06-18T21:06:24.292Z"
|
||||
last_updated: "2026-06-18T21:14:13.706Z"
|
||||
last_activity: 2026-06-18
|
||||
last_activity_desc: Phase 17 complete, transitioned to Phase 18
|
||||
last_activity_desc: Phase 20 execution started
|
||||
progress:
|
||||
total_phases: 27
|
||||
completed_phases: 12
|
||||
total_plans: 55
|
||||
total_plans: 58
|
||||
completed_plans: 54
|
||||
percent: 44
|
||||
---
|
||||
@@ -24,14 +24,14 @@ progress:
|
||||
See: .planning/PROJECT.md (updated 2026-06-16)
|
||||
|
||||
**Core value:** One color-coded family calendar (shared + personal) and shared lists from a single low-friction PWA — cross-ecosystem, no app store
|
||||
**Current focus:** Phase 17 — ui-optimization-polish
|
||||
**Current focus:** Phase 20 — admin-member-editor-form-declutter
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 18 — Auto timezone detection and ability to change timezone
|
||||
Plan: Not started
|
||||
Status: Ready to execute
|
||||
Last activity: 2026-06-18 — Phase 17 complete, transitioned to Phase 18
|
||||
Phase: 20 (admin-member-editor-form-declutter) — EXECUTING
|
||||
Plan: 1 of 3
|
||||
Status: Executing Phase 20
|
||||
Last activity: 2026-06-18 — Phase 20 execution started
|
||||
|
||||
### ✅ Resolved Checkpoint — Phase 15 Plan 15-03 Task 2 (human-action)
|
||||
|
||||
|
||||