docs(04-01): complete lists foundation plan

This commit is contained in:
Lucas Berger
2026-06-09 12:06:53 -04:00
parent c0088edf44
commit 0fd4d66ee7
4 changed files with 172 additions and 21 deletions
+11 -9
View File
@@ -4,13 +4,13 @@ milestone: v1.0
milestone_name: milestone
status: executing
stopped_at: Phase 4 UI-SPEC approved
last_updated: "2026-06-09T14:25:21.889Z"
last_activity: 2026-06-09 -- Phase 04 planning complete
last_updated: "2026-06-09T16:06:41.661Z"
last_activity: 2026-06-09 -- Phase 04 execution started
progress:
total_phases: 15
completed_phases: 3
total_plans: 21
completed_plans: 21
total_plans: 27
completed_plans: 22
percent: 20
---
@@ -21,14 +21,14 @@ progress:
See: .planning/PROJECT.md (updated 2026-06-07)
**Core value:** One color-coded family calendar (shared + personal) and shared lists from a single low-friction PWA — cross-ecosystem, no app store
**Current focus:** Phase 04 — Shared Lists + Live Sync (entry gate: SSE-over-Pangolin smoke test, D-14)
**Current focus:** Phase 04 — shared-lists-live-sync
## Current Position
Phase: 4
Plan: Not started
Phase: 04 (shared-lists-live-sync) — EXECUTING
Plan: 2 of 6
Status: Ready to execute
Last activity: 2026-06-09 -- Phase 04 planning complete
Last activity: 2026-06-09 -- Phase 04 execution started
Progress: [█████░░░░░] 50% (3 of 6 phases)
@@ -59,6 +59,7 @@ Progress: [█████░░░░░] 50% (3 of 6 phases)
| Phase 03 P03-07 | 5 | 2 tasks | 7 files |
| Phase 03 P03-04 | 15 | 2 tasks | 3 files |
| Phase 03 P03-05 | 6 | 3 tasks | 6 files |
| Phase 04 P01 | 65 | 4 tasks | 17 files |
## Accumulated Context
@@ -86,6 +87,7 @@ Recent decisions affecting current work:
- [Phase ?]: D-01 calendar default: last-used URL from localStorage (eventForm.lastCalendarUrl), first writable calendar as fallback
- [Phase ?]: D-02 calendar picker: hidden when writableCalendars.length === 1, shown when >1 — authoritative from GET /api/events/writable-calendars
- [Phase ?]: T-03-15 XSS: EventForm renders all values as plain-text JSX children; no dangerouslySetInnerHTML in code
- [Phase ?]: Phase 4 Plan 1
### Roadmap Evolution
@@ -126,6 +128,6 @@ Recent decisions affecting current work:
## Session Continuity
Last session: 2026-06-09T13:44:22.701Z
Last session: 2026-06-09T16:06:41.648Z
Stopped at: Phase 4 UI-SPEC approved
Resume file: .planning/phases/04-shared-lists-live-sync/04-UI-SPEC.md